Sunday, September 6, 2009

9.5.09

Rob started adding audio cable (the white cable hanging down) so we could add speakers later.


We also put it out on the back patio...

Hook ups for the air conditioners


Light Buff mortar... or a HUGE sand pit to climb in according to Christian

BRICKS!

Tuesday, September 1, 2009

Rough-In

It's been awhile, so what's new with the house? We have had plumbing including the kids tub/showers, HVAC come and put the vents in, J&K Electric put in our wiring, plugs, light switches, etc. And, ADT was out yesterday making sure we didn't have any windows that 3 teenage daughters could eventually sneak out of!

All of our electrical wiring meeting down in the garage as well as one of our AC trunk lines. We have one in the garage for the basement and main level. We also have another one in the attic for the kids level.

The view through our closet into our bathroom. On the right is my washer and dryer connections in the closet. Our laundry room will be upstairs with the kids so why not have my own in my closet?! Now all there is to do... teach the kids to do their own laundry!

View from the front door/study area. We have a plug and cable in the wall for the TV to hang on the wall, no little fingers changing the channel! There are can lights, plugs, and light/fan set ups. AND, 7 outlets in the kitchen. Woohoo!

View from Rie's room into the hall through the right door, her closet are the left doors. Past the closet is the laundry room and the upstairs living area with a view of the fields and "mountains."

Hopefully we will have a rough-in inspection by the end of the week.
Then, we'll start sheet rock and brick!

Thursday, August 20, 2009

An update, finally

I'm finally back online with a camera that is working. We have Renai water heater lines going in.


Here is the Renai panel.

And our duct work is going up.

Our fireplace has finally made its debut.

And the opened up the top window again. First it was big and then they made it smaller because we added the eyebrow expansion roof under the window. But, we decided we wanted the bigger window anyway.

Monday, August 10, 2009

Monday, 8.10.09

We have a concrete pad for our fireplace and a rough in plumbing as of today. I am posting pictures, but framing is hard to see in a picture.


Kaden's bathroom

utility room

I forgot to post this picture last week. Our back porch.


Friday, August 7, 2009

Thursday

Looks like the framing crew is finished, but we found a few things they didn't do. Other than that we are very happy. Coming along and they're doing a great job!

Tuesday, August 4, 2009

one week later...

It's officially one week since we started framing the house and look how far we've come! We hope to put shingles, doors, and windows on by the weekend. Amazing. Can't wait to see what another week brings. Keep watching...

Front of the house

Back of the house

The view from our kitchen windows and door.

2nd floor

Front view from Rie's room

Upstairs playroom

View from the front door, except our stairs are not curved yet. To the right is the dining room to where the framed beams are up front. Beyond that is our living room and kitchen. Behind the stairs leads to the master suite.

How the back porch is tied into the main house frame.

Our family enjoying the process.

The kids and I looking out the master bedroom door that leads to the back porch. Of course we always have a comedian...

Monday, August 3, 2009

Friday and Saturday

Friday was the main level day. The exterior and interior walls went up, as well as stairs from the basement.





Saturday morning we met our project manager, Scotty, at the site. We even had a few changes and by the time we came back at 4 pm they had already fixed them. And, they started framing out the second floor.




back of the house