Tuesday, July 28, 2009

Concrete and rain!

Monday the workers put out the plastic coating and rebar that ties into the basement walls. We weren't sure when the concrete would be poured because the afternoon sun was too hot and rain was predicted for today. But, thankfully Alabama Concrete showed up by 7 am and they began their process. Rob was out there for awhile and made sure it looked good. By 9 am it was raining. Yep! When Rob went back out at noon they had fans over the concrete drying it and wiping the rain off. Thankfully it wasn't a hard rain! When Rob was leaving the site again our trusses and floor system showed up. Now we'll see what the weather has in store for us and our new house for the rest of the week.